1. Task advise 24h before start

Result (pass or not pass) - Item 1

2. Check of cable conformity

Result (pass or not pass) - Item 2
Drag & Drop Files, Choose Files to Upload Puoi caricare fino a 3 file.

3. Test of insulation resistance and continuity

Result (pass or not pass) - Item 3
Drag & Drop Files, Choose Files to Upload Puoi caricare fino a 3 file.

4. Check of presence of damage and if damage is reparable (if any)

Result (pass or not pass) - Item 4
Drag & Drop Files, Choose Files to Upload Puoi caricare fino a 3 file.

5. Written approval of Client of damage reparation (if any)

Result (pass or not pass) - Item 5
Drag & Drop Files, Choose Files to Upload Puoi caricare fino a 3 file.

6. Reparation and check (if any)

Result (pass or not pass) - Item 6
Drag & Drop Files, Choose Files to Upload Puoi caricare fino a 3 file.

7. Check of the cable laying and backfilling

Result (pass or not pass) - Item 7
Drag & Drop Files, Choose Files to Upload Puoi caricare fino a 3 file.

8. Test of electrical continuity after laying

Result (pass or not pass) - Item 8
Drag & Drop Files, Choose Files to Upload Puoi caricare fino a 3 file.

9. Check of the wiring of the cable inside test post

Result (pass or not pass) - Item 9
Drag & Drop Files, Choose Files to Upload Puoi caricare fino a 3 file.

10. Pull test of cable connections with crimped butt connectors (in case of connection between two cables)

Result (pass or not pass) - Item 10
Drag & Drop Files, Choose Files to Upload Puoi caricare fino a 3 file.

11. Check of splicing kit installation (in case of cables connection)

Result (pass or not pass) - Item 11
Drag & Drop Files, Choose Files to Upload Puoi caricare fino a 3 file.

12. Check of wiring inside TP or JB

Result (pass or not pass) - Item 12
Drag & Drop Files, Choose Files to Upload Puoi caricare fino a 3 file.

13.As Built red copy

Result (pass or not pass) - Item 13
Drag & Drop Files, Choose Files to Upload Puoi caricare fino a 3 file.

Company Approval SNAM

Cancella la firma
This signature will be used exclusively for this document

CP 3rd Level Technician Supervisor FM Engineering (PF)

Cancella la firma
This signature will be used exclusively for this document

Executing Company SCOGAT

Cancella la firma
This signature will be used exclusively for this document